Mumbai family pay EMIs for undelivered flat; builder ordered to pay Rs 83 lakh
A Mumbai builder has been directed to refund Rs 83.56 lakh to flat buyers due to significant delays. The commission found that construction completion was only about 50% to 60% at the time of the complaint. Flat buyers had not received possession as stipulated in their agreement from February 2019. The buyers faced financial hardships, including incorrect EMI payments that began in August 2020.
Read at Times of India(opens in a new tab)
Full coverage
Mumbai family pay EMIs for undelivered flat; builder ordered to pay Rs 83 lakh (opens Times of India in a new tab)
A Mumbai builder has been directed to refund Rs 83.56 lakh to flat buyers due to significant delays. The commission found that construction completion was only about 50% to 60% at the time of the complaint. Flat buyers had not received possession as…